Objective: Installation & commissioning of 1 x 7.5/15MVA, 33/11.5kV transformers
Scope of Work
Design, manufacture and testing of 1 x 7.5/15MVA, 33/11.5kV, ONAN/ONAF power transformer.
Full in-house routine, comprising of zero sequence impedance, lightening impulse with chopped wave, temperature rise and noise test.
Delivery using a short file steerable trailer for site access then off-loading via hydraulic jacking and skating including rotation of unit and a one directional skid of 10m including pre-commissioning works as per the customers specification by our Substation Services installation & commissioning teams.