Sebergham, Cumbria
See more Case Studies
Overview
Client:
Undisclosed
Location:
Sebergham, Cumbria
Objective:
Installation & commissioning of 1 x 4/8MVA, 33/11kV transformer
Scope of Work
Manufacture and testing of 1 x 4/8MVA, 33/11kV, ONAN/ONAF transformer.
Full in-house routine, including partial discharge testing.
Delivery & off-loading the fully built transformer at the customers site using 80T mobile crane.
Pre-commissioning works as per the customers specification by our Substation Services installation & commissioning team.